Background
THB was employed to carry out remedial works to various CAZOO car park sites across the UK, including: Milbrook, Chertsey, Newport, and Milton Keynes. The scope of works included;
- Removal of Trees and overgrown vegetation.
- Breakout of existing subsided parking areas, Excavate and expose areas for new Sub-base.
- Reinstate Subbase with Geotextile membrane and Type 1.
- Supply and installation of precast concrete kerbing to tie in to the existing area.
- Supply and install new asphalt: AC20, AC10 and SMA10.
- Excavate and install new drainage including ACO drains, Catch pits, and New Gullies.
- Supply and installation of new service ducts and draw pits.
- Removal of existing fencing and Street Furniture.
- Installation of road and parking bay markings.
- Concrete Repairs
Before & After
Before
After
Objectives
- The scope of work was to be completed in 6 weeks with minimal disruption to everyday operations.
Challenges
- Dense vegetation removal
- Installation of new drainage
- Time constraints
Outcome
THB completed all the required work on time with no delays across all four Cazoo sites. The result of the project ensured a safer and smarter environment for colleagues and customers. With additional drainage installed, the car park was less susceptible to flooding.
Why Choose THB?
24/7 Callout Service
Safe Contractor Approved
Award Winning
BBA Approved Installer
Construction Line Gold Member
Part Of The National Highways Schemes
UKAS Management Systems
Environmentally Aware
Get In Touch
For a quick response simply fill out our form. A member of our friendly team will get straight back to you.
Our Accreditations, Certifications & Registrations